REHABILITATION OF THE OVERPASS FROM THE DAVID AGHMASHENEBELI AVENUE TO MUKHATGVERDI IN TBILISI

Completion of the preparatory work - July 2015.
Start of construction of retaining walls - August, 2015.
The total area of the walls erected by Reinforced Earth technology will be 2400 sq. meters.
Completion of the project is scheduled for the end of November, 2015.
Customer - "New Line" ltd
General Customer - Tbilisi City Hall
01.06.2015