Zestafoni- Kutaisi-Samtredia Highway (E 60) Section: New Kutaisi Bypass KM 0+000 - KM 17+300
Customer:
Design was Developed by TRANSPROJECT Ltd:
Design of the Retaining Walls:
Geotechnical Survey was Carried out by:
Contractor: J.V. Todini, Takenaka
Subcontractor - AKKORD-GEORGIA:
Engineer - J.V. PADECO:
Project includes erection of 2 ramps (4 Reinforced Earth retaining walls).
Total area is about 600 sq. m.
Implementation of this project was finished in May, 2014